Replacing The Sealing Set On Tool Flange Of Hygienic Robots - ABB IRB 1200 Product Manual

Hide thumbs Also See for IRB 1200:
Table of Contents

Advertisement

3 Maintenance

3.4.2 Replacing the sealing set on tool flange of Hygienic robots

3.4.2 Replacing the sealing set on tool flange of Hygienic robots
General
To ensure the sealing efficiency, sealing parts on the tool flange of Hygienic robots
is recommended to be replaced at an interval of 12 months or 60000 operating
hours.
Location of the sealing set
Parts of the sealing set on the tool flange of Hygienic robots are located as shown
in the figure.
xx2100001485
A
B
C
D
E
Required spare parts
Continues on next page
144
Gasket, axis 6, Hygienic
Seal ring unit
Stainless shaft
Sealing washer
Stainless screws
Note
The spare part numbers that are listed in the table can be out of date. See the
latest spare parts of the IRB 1200 via myABB Business Portal,
www.abb.com/myABB.
© Copyright 2014 - 2021 ABB. All rights reserved.
Recommended to replace at a 12-month interval.
Recommended to replace at a 12-month interval.
Replace if damaged.
Recommended to replace at a 12-month interval.
Replace if damaged.
Product manual - IRB 1200
3HAC046983-001 Revision: S