DAT-LINE (Data Line Port)
System Technician-Demanded Tests:
Descriptions and Error Codes
Always investigate tests in the order presented in the table below. By clearing
error codes associated with the Digital Looparound test, for example, you may
also clear errors generated from other tests in the testing sequence. For
example, you may also clear errors generated from other tests in the testing
sequence.
Order of Investigation
Digital Looparound test (#171)
NPE Crosstalk test (#6)
Conference Circuit test (#7)
Audit Update test (#36)
1.
D = Destructive; ND = Nondestructive
NPE Crosstalk Test (#6)
The NPE Crosstalk test verifies that this port's NPE channel talks on the selected
time slot and never crosses over to time slots reserved for other connections. If
the NPE is not working correctly, 1-way and noisy connections may be observed.
This test is usually part of a port's long test sequence and executes in about 20 to
30 seconds.
Table 8-198. Test #6 NPE Crosstalk Test
Error
Test
Code
Result
Description / Recommendation
ABORT
Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals up to 5 times.
1000
ABORT
System resources required to run test are not available. The port may be in
use on a valid call. Use status data-module to determine when the port is
available for testing.
1. Retry the command at 1-minute intervals up to 5 times.
1001
ABORT
Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals up to 5 times.
555-233-143
Short Test
Long Test
Sequence
Sequence
X
X
X
X
X
X
Continued on next page
Issue 1 May 2002
1
D/ND
ND
ND
ND
ND
8-491