11-26
Integration Volume
8. CALLS TO THE INTERCEPT EXTENSION (ATTENDANT) (For new install)
This test verifies that each Octel 200/300 port extension can transfer a call to the intercept
extension (attendant)
a.
Connect telephone B to the modular adapter position associated with port 1 of the Octel
200/300.
b. From telephone A, call the extension number associated with telephone B.
c.
Answer telephone B and perform a hookswitch flash, enter the transfer code, if required; press
0
specified in System Parameter 13.
d. Is telephone A connected to the number called to reach the attendant?
YES
NO
.
9. VERIFYING PORTS
This test verifies that all the PBX port extensions are connected to the correct ports.
a.
From telephone C, call the extension associated with port 1.
b. Does the Octel 200/300 answer with "To enter your mailbox press pound"?
YES
If the Octel 200/300 does not answer, the probable reason is that the PBX port extension is
connected to the wrong physical port.
c.
On the terminal, at the @ prompt, enter the command P S. The port number in the IDL2 state is
the port that Octel 200/300 thinks was called. If that is not the port you intended to call, the lines
should be changed so that the correct line is connected to the correct port.
Enter
d. Call the extension number of the next port. Go to step b. Proceed until all ports are tested.
Octel 200/300
S.4.1
.
(or the attendant's extension number). Then hang up telephone B. Use the transfer code
Continue test for all port extensions, then proceed with step 9.
'
Determine the cause and correct the problem before continuing.
'
- Before continuing with step 9 -
When all Octel 200/300 port extensions pass steps 1−8,
connect the 25-pair cables to the Octel 200/300 ports and
RS-232C cables to the SIC8 I/O panels and test the
system for standard operation. Verify that the yellow
LEDs on the Integration board are ON.
To obtain the desired results, before continuing these tests, verify that all test extensions
are configured as mailboxes.
go to step e.
'
, then hang up.
9
9
S T O P