Maintenance Objects
When plugged into the port in this manner, the test set establishes a signaling link
connection with the switch and attempts to complete SPID initialization by using
the Service SPID administered for the system (see the System Maintenance
Administration Form). If the test set displays the correct administered port address
for the endpoint or adjunct under test, the test passes (see Service SPID Display
which follows). If after one minute nothing is displayed on the test set, the test
fails.
Table 130. SPID Facility Test
Test
Result
FAIL
No response is received from the endpoint.
1. Check the physical wiring between the switch and the endpoint or adjunct.
FAIL
Display does not match administered port address for the endpoint or adjunct.
1. Change station administration for endpoint or adjunct to match displayed port
address.
PASS
Display matches administered port address for the endpoint or adjunct.
For BRI endpoints:
1. Verify that the SPID values administered in the switch and the endpoint are
consistent.
2. If the SPID values are correct, replace the endpoint.
For ASAI adjuncts:
1. Verify that the TEI values administered in the switch and the adjunct are consistent.
2. If the TEI values are correct, consult the recommended repair procedures of the
manufacturer for the adjunct.
The abbreviations used in (Service SPID Display) have the following meanings:
P
C
SS
pp
ext
SPID
844
Issue 5 October 2002
Description/ Recommendation
port network (1,2, etc.)
Carrier (A,B,C, etc.)
Slot (01, 02, etc.)
port (01-12)
extension one and two (one through 99999)
service order profile identifier
Continued on next page