Creating a Mass Floor Schedule
After
creating mass
to analyze the design. If you change the shape of the mass, the mass floor schedule updates to reflect the
changes.
To create a mass floor schedule
1 Click View menu
2 In the New Schedule dialog, do the following:
3 In the Schedule Properties dialog, do the following:
The schedule displays in the drawing area. If you included the Usage field in the schedule, you can assign
a usage to each mass floor in the schedule.
Related topics
Examples of Conceptual Design Analysis
Schedule Views
floors, you can create a schedule for them. Use a mass floor schedule to assign usages or
New
Schedule/Quantities.
a For Category, click Mass Floor.
b For Name, specify the schedule name.
c Select Schedule building components.
d Click OK.
a On the Fields tab, select the desired fields.
See
Selecting Fields for a Schedule
b Use other tabs to specify filtering, sorting, and formatting of the schedule.
See
Specifying Schedule Properties
c Click OK.
on page 124
Schedule/Quantities, or on the View tab of the Design Bar, click
on page 128.
on page 128.
on page 529
Creating a Mass Floor Schedule | 527