Commissioning; Turning On The Pbx - Auerswald COMpact 3000 analog Operating Manual

Table of Contents

Advertisement

Commissioning

The commissioning of the PBX includes switching on the PBX, as well as connecting the PC
for configuration. If the VoIP and ISDN end devices are connected, they also have to be
commissioned.

Turning on the PBX

Requirements:
– The power supply unit included in the package
– For connecting to the power supply unit (step 1): cover panel is removed
1. Insert the barrel connector of the power supply unit into the barrel socket of the PBX.
The figure in the following shows the position of the barrel socket under the cover
panel, as well as the connection set up to the power supply unit.
2. Replace the cover panel.
3. Insert the power supply unit into a freely accessible 230 V Schuko socket
The "Power" LED shines several seconds in red and orange, as specified below. If
the LEDs shines green, the PBX is ready for operation.
"Power" LED:
Shines red
Shines orange
Blinks orange
Shines orange
Shines green
COMpact 3000 analog/ISDN/VoIP - Firmware V4.0 - Operating Manual V06 12/2020
Status of the PBX:
The boot partition is being tested.
The hardware data and the kernel are being loaded from
the partition.
The kernel drivers are being loaded.
The PBX application is started.
The PBX is ready for operation.
Installation and Commissioning
Commissioning
Turning on the PBX
75