SSANGYONG Y200
M162 ENGINE MECHANICAL 1B1-15
Removal & Installation Procedure
1. Remove the poly v-belt.
2. Remove the tensioning pulley by turning its
mounting nut counter clockwise as shown in figure.
Installation Notice
Tightening Torque
YAD1B250
3. Remove the bolts and remove the water pump
pulley.
Installation Notice
Tightening Torque
4. Remove the mounting bolts(M8 x 30, 3 pieces) at
the tensioning device, and remove the tensioning
device.
Installation Notice
Tightening Torque
YAD1B360
5. Installation should follow the removal procedure
in the reverse order.
40.5 - 49.5 N•m
(29.9 - 36.5 lb-ft)
22.5 - 27.5 N•m
(16.6 - 20.3 lb-ft)
26 - 32 N•m (19 - 24 lb-ft)