SSANGYONG Rexton Y200 Manual page 683

Hide thumbs Also See for Rexton Y200:
Table of Contents

Advertisement

SSANGYONG Y200
DIESEL ENGINE CONTROLS 1F3-59
Tools Required
000 589 77 03 00 Box Wrench Insert
601 589 00 08 00 Flange
601 589 05 21 00 Locking Screw
601 589 05 14 00 Assembly Cage
Removal Procedure
1. Position the no.1 cylinder at 15° ATDC.
Notice: Do not rotate the engine in opposition
direction of engine rotation.
YAD1BC10
2. Remove the connecting rod (9).
3. Disconnect the vacuum lines (13, 14).
4. Remove the accelerator control damper (10).
(Manual transmission vehicle)
YAD1FCW0
5. Remove the suction line (16) and pressure line
(4).
6. Remove the banjo bolt (1) and then remove the
seal (2) and fuel line (3).
7. Remove the plastic clip (8) on the injection line.
YAD1FCX0
8. Disconnect the injection lines (15) from the
injection pump (25).
9. Remove the banjo bolt (6) and then remove the
seal (7) and return line (5).
YAD1FCY0

Advertisement

Table of Contents
loading

Table of Contents