Installation Procedure
1. Carefully place the new Belt into position around the Driver and Idler
Pulleys.
2. Adjust the Belt tension.
3. Replace the Wire Control Bracket.
4. Replace all Cables moved during the Belt Removal process.
5. Do REP 2.18
Solenoid Replacement, Diverter Solenoid (L1)
the Diverter Solenoid.
6. Do REP 1.1
Top Cover Replacement
7. Connect the Power Cord.
8. Power ON the eWire.
GBC eWire
to Install
to replace the Top Cover.

REP 2.9 Bypass Timing Belt #2 Replacement

There are two timing belts used at the rear of the eWire Upper Bypass
Assembly. The procedure below can be used for the downstream (paper
exit side) Belt.
Type of Belt
Belt, 502T, 2MM 2GT
Belt, 555T, 2MM 2GT
Removal Procedure
1. Turn power OFF to the eWire.
2. Remove the Power Cord.
3. Do REP 1.1
Top Cover Replacement
4. Do REP 2.18
Solenoid Replacement, Diverter Solenoid (L1)
remove the Diverter Solenoid
5. Disconnect the wires from the M2 Bypass Stepper Motor.
6. Relieve tension on the Belt by loosening the M4 screws (2) on the
Belt Tensioner.
7. Carefully remove the Belt by lifting it off of the Idler Pulleys and Drive
Pulleys and remove the old Belt.
01/26/2018
4-25
Location
Motor
Upstream
M1
Downstream
M2
to remove the Top Cover.
Repairs/Adjustments
to

Advertisement

Table of Contents
loading

Table of Contents