8.7. Level the eWire

1. Check the level of the eWire front to rear.
2. Check the level of the eWire left to right.
3. If adjustment is needed, remove the side plates to access the
casters. Loosen the jam nut underneath the caster and raise or
lower the caster using an adjustable wrench.
4. Repeat the process for all necessary casters. Repeat steps 1 and
2 and make additional adjustments if needed.
5. Tighten the jam nut on each caster and replace the side covers.
Installation Instructions

8.8. Power Up the eWire

Do the following to power up the eWire.
1. Check the Volt and Hertz specifications on the Serial number label
to ensure that the input power at the site matches the power
requirements of the EWire.
2. Connect the Power Cord to the AC Filter on the rear of the EWire.
3. Connect the Upstream DFA Cable to the EWire.