To install the Oven Cryo System
1. Put the GC in standby condition.
2. Cool the oven, injectors, and detectors to room temperature.
Note By pressing the Maintenance button, the GC cool down is automatically
carried out.
3. Close the gas supplies.
4. Power off the GC.
a. Push down the power switch (breaker), located at the back of the instrument, in the
position O.
b. Unplug the power cable from the AC Input connector into the back of the GC and
from the wall outlet.
5. If external modules are present, unplug the power cable from the AC Input connector of
each external module, and from the wall outlet.
6. Remove the Left Side panel.
a. Open the front door of the GC. Using a T20 Torxhead screwdriver, unscrew the left
side panel screw from the interior front panel. See
Figure 546. Left Side Panel Fixing Screw
b. Slide the panel towards the back of the instrument up to the stop.
c. Remove the panel by pulling it outwards. Be aware that the ground wire is attached
to the panel. See
Figure
547.
Figure
546.
Thermo Scientific

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Trace 1610

Table of Contents