SUPPLIES
Anchoring kits:
For Gantry:
5 securing screws (1).
5 anchoring inserts (2).
3 leveling screws(3).
3 jack feet (4).
6 caps for holes (5).
For Control Station
4 securing screws.
4 anchoring inserts.
4 jack feet.
2
TOOLS
Standard Tool Box
Drill and drill bits (drill bit sizes and hole depths vary according to the bolts used - see
Inserts Provided with the Senographe System (only for non-seismic areas) on page 354
ing Inserts Not Provided with the Senographe System (for seismic areas) on page
3
REQUIRED EFFORT
Personnel: 1 Field Engineer
Time: 60 minutes
4
SAFETY PRECAUTIONS
CAUTION
Follow standard safety practices for handling heavy equipment.
Never push on the covers to move the Gantry on its wheels. Push the base, or if necessary
pull on the large handle.
Before moving the Control Station on its transportation wheels, ensure that the wheels are
oriented in the desired direction of movement. If not, the Control Station can tip over.
JC-PHY-A-003.fm
Service Information and Procedures Class A 2385072-16-8EN
Job Card PHY A003 - Gantry and Control Station Installation
1
2
Page no. 401
Senographe DS
3
4
5
Anchoring
355)).
Chapter 6
and
Anchor-
Chapter 6

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents