Job Card PHY A014 - Connect Gantry to Control Station

1
SUPPLIES
None
2
TOOLS
Standard Tool Box
3
REQUIRED EFFORT
Personnel: 1 Field Engineer
Time: 30 minutes
4
SAFETY PRECAUTIONS
None
5
PREREQUISITES
None
6
PROCEDURE
6-1
Black Tubular Harness Routing
Gantry to Control Station cables are already connected in the Gantry. The harness (Control Station -
Positioner harness) leaves the Gantry through a black tubular conduit.
1. Run the cable conduit from the Gantry to the control station (through floor or wall ducting as appropri-
ate).
2. The conduit can enter the control station cabinet from either side. If it enters from the left (as viewed
from the front), it must pass through the space at the bottom of the cabinet to emerge on the right-
hand side.
3. Place all of the cables leaving the conduit under the bottom level (you will route them in the next sec-
tion).
4. Use the clamp provided to secure the conduit to the metal chassis at (A). If the conduit is too long for
the cable run, it can be cut. Take care not to damage the cables.
A
JC-PHY-A-014.fm
Service Information and Procedures Class A 2385072-16-8EN
Job Card PHY A014 - Connect Gantry to Control Station
Page no. 455
Senographe DS
Chapter 6
Note: At this stage, all of the ca-
bles are underneath the bottom
level.
Chapter 6

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Senographe DS and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents

Save PDF