3 Installation and commissioning

3.8 Test run after installation, maintenance, or repair

3.8 Test run after installation, maintenance, or repair
Safe handling
Use the following procedure after installation, maintenance, or repair, before
initiating motion.
1
2
3
4
5
6
7
8
Collision risks
92
DANGER
Initiating motion without fulfilling the following aspects, may increase the risk for
injury or cause damage to the robot.
Action
Remove all tools and foreign objects from the robot and its working area.
Verify that the robot is properly secured to its position by all screws, before it is powered
up.
Verify that any safety equipment installed to secure the position or restrict the robot
motion during service activity is removed.
Verify that the fixture and work piece are well secured, if applicable.
Verify that all safety equipment is installed, as designed for the application.
Verify that no personnel are inside the safeguarded space.
If maintenance or repair has been done, verify the function of the part that was main-
tained.
Verify the application in the operating mode manual reduced speed.
CAUTION
When programming the movements of the robot, always identify potential collision
risks before initiating motion.
© Copyright 2019-2022 ABB. All rights reserved.
Product manual - IRB 1100
3HAC064992-001 Revision: L