Figure 61
Fibers 4 and 6 deactivated
The disable fibers will be skipped while moving to the next fiber test.
If Disable Fiber Test is pressed while a tested fiber is selected, a dialog
box displays: «You're about to delete acquisition files. Are you
sure?».
Click on Yes to confirm the deactivation, and by consequence, to delete cor-
responding trace(s).
Click on No to cancel the deactivation.
To activate the fiber, select it and press Enable Fiber Test.

Testing MPO

Once the project is opened, the OTDR acquisitions can be launched.
1
Connect the Switch to the Platform, via a USB cable.
2
Activate the USB Switch icon on the Platform
3
On the Project page, select the label or fiber to be tested.
If a label is selected (highlighted in blue), all the active fibers of this label will be
tested one after the other.
If one fiber number is selected (in blue), the test will be performed exclusively for
this fiber.
4
Press S
The fiber number being tested in displayed on the Switch.
5
Once a test is completed, a dialog box is displayed to test for next label/fiber.
Enterprise-SLM Software option (T-BERD/MTS-6000A V2 only)
/S
button to launch the test.
TART
TOP
User Manual
Chapter 3 Reflectometry measurements
78000010220 Rev. 024
119