Confirm the system message of the Telephony Server side.
Confirm that the MG-BRI is physically connected to ISDN network.
Also confirm the line cable between:
- MDF and MG-BRI
- MDF and DSU
Confirm the data assignment of the Telephony Server side and MG-BRI side.
Telephony Server: Is the data assignment correct?
MG-BRI: Confirm the configuration data assigned from the maintenance console.
[Turned ON]
Proceed to STEP 5.
Operate the connection test passing through the MG-BRI. Was the call origination/termination OK?
STEP 5
[Call origination/termination did not operate normally]
Confirm the system message of the Telephony Server side.
Confirm that the MG-BRI is physically connected to ISDN network.
Also confirm the line cable between:
- MDF and MG-BRI
- MDF and DSU
Confirm that the cable is not damaged (Operate the link test)
Confirm the data assignment of the Telephony Server side and MG-BRI side.
Telephony Server: Is the data assignment correct?
MG-BRI: Confirm the configuration data assigned from the maintenance console.
Confirm the contract status of the ISDN line.
[B lamp of LINE0/1 does not turn ON or does not flash]
Indicates that all channels are in idle state, confirm the office data assignment.
[B lamp of LINE0/1 flashes]
Slow flash: Make-Busy is assigned to either one of the channel and other in idle state, confirm the
office data assignment.
Fast flash: Make-Busy is assigned to both of B1, B2 channels, confirm the office data assignment.