DLP- D357 Verify Pass-Through Circuits

DLP-D357 Verify Pass-Through Circuits
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
In the CTC Circuits window, choose a circuit that passes through the node that will be removed and click
Step 1
Edit.
Step 2
In the Edit Circuits window, check Show Detailed Map.
Verify that the circuits have the same east and west port VC4, VC3, VC11, and VC12 mapping. For
Step 3
example, if the circuit west port mapping is s5/p1/V1 (Slot 5, Port 1, VC4 1), verify that the east port is
also VC4 1. If the circuit has different east/west VC4s and/or VC3, VC11, or VC12s, record the name
of the circuit.
Figure 20-13
Step 4
Repeat Steps
Step 5
Delete and recreate each circuit recorded in Step 3. To delete the circuit, see the
Circuits" procedure on page
Tunnels."
Return to your originating procedure (NTP).
Step 6
Cisco ONS 15454 SDH Procedure Guide, R7.0
20-64
This task verifies that circuits passing through a node that will be removed
enter and exit the node on the same VC4 and/or VC3, VC11, or VC12.
None
DLP-D60 Log into CTC, page 17-49
As needed
Onsite or remote
Provisioning or higher
Figure 20-13
shows a circuit passing through a node (doc-124) on the same VC4 (VC4 2).
Verifying Pass-Through VC4s
1
to
3
for each circuit that appears in the Circuits tab.
17-21. To create the circuit, see
Chapter 20
"DLP-D27 Delete
Chapter 6, "Create Circuits and Low-Order
DLPs D300 to D399
78-17194-01