MANUAL TRANSMISSION
(d) Connect the exhaust pipe to the catalytic converter
Torque: 39 N . m (400 kgf–cm, 29 ft–lbf)
11.–2(22R–E)
INSTALL EXHAUST PIPE, BRACKET AND CLAMP
(a) Install the exhaust pipe to the manifold.
Torque: 62 N – m (630 kgf – cm, 46 ft – Ibf)
(b) Install the pipe bracket to the clutch housing.
Torque the bolts.
Torque: Upper 19 N–m (195 kgf–cm, 14 ft –Ibf)
(c) Install the exhaust pipe clamp.
Torque: 19 N – m 1195 kgf – cm, 14 ft – Ibf)
12.–1(3VZ–E)
INSTALL CLUTCH RELEASE CYLINDER
Install clutch release cylinder and torque the
two bolts.
Torque: 12 N – m (120 kgf – cm, 9 ft – Ibf )
12.–2(22R–E)
INSTALL STARTER MOUNTING BOLTS, CLUTCH
RELEASE CYLINDER AND TUBE BRACKET
(a) Install tube bracket and torque the starter lower
mounting bolt and nut.
Torque: 39 N – m (400 kgf – cm, 29 ft – Ibf)
(b) Install clutch release cylinder and torque the two
bolts.
Torque: 12 N – m (120 kgf – cm, 9 ft – Ibf)
13.(R150F, G58)
INSTALL PROPELLER SHAFT DUST COVER
SUBASSEMBLY
(a) Install the cover.
(b) Install and torque the three bolts.
Torque:
A–bolt 36 N – m (370 kgf – cm, 27 ft–lbf )
B–bolt 23 N – m (230 kgf – cm, 17 ft – Ibf )
Installation of Transmission with Transfer
front side, and torque the bolts.
Lower 69 N – m (700 kgf – cm, 51 ft – Ibf )
MT1–23