Action
Remove the guide pins and secure the remaining
two attachment screws.
Pre-tighten the screws crosswise.
Torque tighten all screws crosswise.
Remove the lifting aid by removing the screws.
Clean pushed-out flange sealant, if any.
Action
Reconnect the connectors to the drive board.
D4/5.X1 to X1
D5.DC+ to +DC
D5.DC- to Ground
D4/5.X4 to X4
D5/4.X2 to X2
D4/5.X5 to X5
Connect the connectors to each other and snap
them to the cable holders.
J5/6.DC+ to J6.DC+
J5/6.DC- to J6.DC-
J5/6.CS to J6.CS
J5/6.CP to J6.CP
© Copyright 20212022 ABB. All rights reserved.
Note
xx2000002140
Tightening torque: 1.4 Nm.
xx2000002139
Note
xx2000002138
xx2000002137
Product manual - CRB 15000
3HAC077389-001 Revision: E

Advertisement

Table of Contents
loading

Table of Contents