Table 67: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
device tolerances.
Power
Measure distance between external power
sources and device installation site.
Calculate the power consumption and
requirements.
Rack or Cabinet
Verify that your rack or cabinet meets the
minimum requirements for the installation of
the device.
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor and
building structure.
Cables
Acquire cables and connectors:
Determine the number of cables needed
based on your planned configuration.
Review the maximum distance allowed for
each cable. Choose the length of cable
based on the distance between the
hardware components being connected.
Plan the cable routing and management.
Related
Documentation
214
For More Information
"Environmental Requirements and
Specifications for a QFX3500 Device"
on page 221
"AC Power Specifications for a
QFX3500 Device" on page 299
"Rack Requirements for a QFX3500
Device" on page 235
"Cabinet Requirements for a QFX3500
Device" on page 242
"Clearance Requirements for Airflow
and Hardware Maintenance for a
QFX3500 Device" on page 250
Determining Interface Support for the
QFX3500 Device
"Determining Transceiver Support for
QFabric Systems" on page 258
"Cable Specifications for Console and
Management Connections for the QFX
Series" on page 268
General Safety Guidelines and Warnings on page 329
General Site Guidelines on page 217
Installing and Connecting a QFX3500 Device on page 473
Mounting a QFX3500 Device in a Rack or Cabinet on page 475
Performed By
Date
Copyright © 2018, Juniper Networks, Inc.

Advertisement

Table of Contents
loading

Table of Contents