QFX10002 Site Preparation Checklist

The checklist in
Table 28 on page 64
for a QFX10002 installation.
Table 28: Site Preparation Checklist
Item or Task
Environment
Verify that environmental
factors such as
temperature and humidity
do not exceed switch
tolerances.
Power
Measure the distance
between external power
sources and the switch
installation site.
Calculate the power
consumption and
requirements.
Rack
summarizes the tasks you need to perform when preparing a site
For More
Performed By
Information
"QFX10002
Environmental
Requirements and
Specifications" on
page 66
"QFX10002 AC
Power
Specifications" on
page 52
"QFX10002 DC
Power
Specifications" on
page 57