Chapter 6
Create Circuits and VT Tunnels
At the source node, connect an Ethernet test set to the source port and configure the test set to send and
Step 8
receive the appropriate Ethernet traffic.
Transmit Ethernet frames between both test sets. If you cannot transmit and receive Ethernet traffic
Step 9
between the nodes, repeat Steps
correctly.
Perform protection switch testing appropriate to the SONET topology:
Step 10
Configure your test set according to local site practice. For information about configuring your test set,
see your test set user guide.
After the Ethernet test is complete, print the results or save them to a disk for future reference. For
Step 11
information about printing or saving test results, see your test set user guide.
Stop. You have completed this procedure.
NTP-A147 Create a G-Series STS Circuit
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Complete the
Step 1
If you are already logged in, continue with
If you want to enable the G-Series Ethernet ports, complete the
Step 2
Ports" task on page
If you want to change the default flow control settings, complete the
Step 3
Flow Control Watermarks" task on page
From the View menu, choose Go to Network View.
Step 4
Click the Circuits tab and click Create.
Step 5
In the Create Circuits dialog box, complete the following fields:
Step 6
Click Next.
Step 7
August 2005
For path protection configurations, see the
page
17-95.
For BLSRs see the
"DLP-A91 BLSR Switch Test" task on page
This procedure creates a G-Series circuit.
A G-Series Ethernet card must be installed at one end of the circuit.
NTP-A127 Verify Network Turn Up, page 6-4
As needed
Onsite or remote
Provisioning or higher
"DLP-A60 Log into CTC" task on page 17-66
19-16. (You may provision Ethernet ports before or after the STS circuit is created.)
Circuit Type—Choose STS.
Number of Circuits—Leave the default unchanged (1).
Auto-ranged—Unavailable.
1
through
8
to make sure you configured the Ethernet ports and test set
"DLP-A94 Path Protection Switching Test" task on
Step
4.
21-7.
NTP-A147 Create a G-Series STS Circuit
17-87.
at the node where you will create the circuit.
"DLP-A222 Provision G-Series Ethernet
"DLP-A421 Provision G-Series
Cisco ONS 15454 Procedure Guide, R5.0
6-73