NTP-A299 Convert a Point-to-Point or Linear ADM to a Path
Protection Automatically
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
When upgrading VT tunnels, CTC does not convert the VT tunnel to path protection, but instead creates
Note
a secondary tunnel for the alternate path. The result is two unprotected VT tunnels using alternate paths.
If overhead circuits exist on the network, this procedure is service affecting. The overhead circuits will
Note
drop traffic and have a status of PARTIAL after the upgrade is complete.
Complete the
Step 1
ADM. If you are already logged in, continue with Step 2.
If the point-to-point or linear ADM is 1+1 protected, complete the
Step 2
Group" task on page
From either network or node view, click the Circuits tab. Click the circuit you want to upgrade to select
Step 3
it.
From the Tools menu, choose Topology Upgrade > Convert Unprotected to UPSR.
Step 4
To set the path protection parameters, complete the
Step 5
task on page
Click Next.
Step 6
Complete one of the following tasks:
Step 7
a.
b.
Stop. You have completed this procedure.
December 2004
This procedure upgrades a point-to-point or linear ADM to a path
protection without disrupting traffic. You can upgrade STS, VT, and VT
tunnel circuits to path protection. This option is a single circuit
operation.
None
NTP-A124 Provision a Point-to-Point Network, page 5-3
As needed
Onsite or remote
Provisioning or higher
"DLP-A60 Log into CTC" task on page 17-66
18-23. If the point-to-point or linear ADM is unprotected, continue with
19-12.
To route the new path protection circuit manually, complete
Protection Circuit for a Topology Upgrade" task on page
To route the new path protection circuit automatically, complete
a Path Protection Circuit for a Topology Upgrade" task on page
NTP-A299 Convert a Point-to-Point or Linear ADM to a Path Protection Automatically
"DLP-A218 Provision Path Protection Selectors"
Cisco ONS 15454 Procedure Guide, R5.0
at a node on the point-to-point or linear
"DLP-A155 Delete a Protection
"DLP-A397 Manually Route a Path
20-95.
"DLP-A398 Automatically Route
20-95.
Step 3
13-11