Use these procedures to remove the joint unit.
Preparations before removing the joint unit
1
2
Removing the tool flange
1
2
Product manual - CRB 15000
3HAC077389-001 Revision: L
Action
Jog the robot to the specified position: xxx
Axis 1: No significance.
Axis 2: No significance.
Axis 3: No significance.
Axis 4: No significance.
Axis 5: approximately +20°
Axis 6: 0° (home position)
CAUTION
Jog the axis on which the joint unit is to be re-
placed to home position, to achieve correct cable
routing during replacement of the joint unit.
CAUTION
Turn off all supplies for electrical power to the
robot, before starting the repair work.
Action
Remove the tool flange screws and washers.
CAUTION
Valid for CRB 15000-5/0.95
There is cabling connected between the cover
and the joint unit drive board.
Open the cover with care to avoid damage to the
cabling or the connector(s).
Do not leave the cover in location without being
secured with the attachment screws.
© Copyright 2021 - 2023 ABB. All rights reserved.
5.6.8 Replacing the axis-6 joint unit
Note
xx2100000043
Note
xx2000002155
Continues on next page
5 Repair
Continued