Avaya S8700 Maintenance Manual page 2003

For multi-connect configurations
Hide thumbs Also See for S8700:
Table of Contents

Advertisement

PMS-PRNT/JNL-PRNT (PMS Printer Link)
d. Link idle timer; link comes down. This indicates that the printer device is in
an off-line state, for example, paper jam or paper out. Check the printer
device and act promptly to put it back to on-line state. Enter test journal
wakeup-log | pms-log command to set up the printer link.
System Technician-Demanded Tests:
Descriptions and Error Codes
Always investigate tests in the order presented in the table below. For example,
by clearing error codes associated with the Link Tear Down test (#213), you may
also clear errors generated from other tests in the testing sequence.
Order of Investigation
Link Tear Down test (#213)
Link Retry test (#215)
1.
D = Destructive; ND = Nondestructive
Link Tear Down Test (#213)
This test is destructive.
This test disconnects the existing link between the system and the external printer
device. If the link has been disconnected already, this test just returns PASS.
Every resource allocated for a PMS Printer Link is released after this test.
Table 8-519. Test #213 Link Tear Down Test
Error
Test
Code
Result
Description / Recommendation
40
ABORT
Internal system error.
50
ABORT
Internal system error.
1. Retry the command at 1-minute intervals up to 5 times.
1010
ABORT
The link has been busied out to out-of-service.
1. Enter release journal wakeup-log|pms-log command to release the link
2. Retry test journal wakeup-log|pms-log l command to execute the test.
2012
ABORT
Internal system error.
1. Retry the command at 1-minute intervals up to 5 times.
FAIL
Internal System error.
1. Retry the command at 1-minute intervals up to 5 times.
PASS
The link is torn down.
555-233-143
Short Test
Sequence
X
from busyout state.
Long Test
1
Sequence
D/ND
X
D
X
ND
Issue 1 May 2002
8-1281

Advertisement

Table of Contents
loading

Table of Contents