Step 6 Run:
timeout time
The timeout period for waiting for the IGMP Tracert-Response packet is set.
Step 7 Run:
probe-count number
The maximum number of times for the querier to initiate MTrace operations in the timeout
situations is set. The querier re-initiates an MTrace operation if receiving no IGMP Tracert
Response packet within the timeout period.
Step 8 Run:
quit
Exit from the test instance view.
----End

6.21.5 Starting the NQA MTrace Test

This part describes how to start the MTrace test instance to perform the MTrace test for the
multicast path from the multicast source to the querier.
Context
Do as follows on the switch that functions as the NQA client:
Procedure
Step 1 Run:
system-view
The system view is displayed.
Step 2 Run:
nqa test-instance admin-name test-name
The test instance view is displayed.
Step 3 Run:
start now
The NQA MTrace test is started.
Step 4 Run:
quit
Exit from the test instance view.
----End

6.21.6 Checking the Configuration

After performing the MTrace test for the multicast path from the multicast source to the querier,
you can view the test result.
Issue 01 (2012-03-15)
NOTE
The start mode of the MTrace test is the same as that of other NQA tests. Here, take one mode as an example.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 NQA Configuration
328

Advertisement

Table of Contents
loading

This manual is also suitable for:

S9300e

Table of Contents