DLP- G26 Install the TL1 Craft Interface (ANSI Only)
Figure 1-27
Figure 1-27 Installing the Rear Cover with Spacers
Continue with the
Step 6
Stop. You have completed this procedure.
NTP-G14 Install DWDM Equipment
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Complete the
Step 1
Complete the
Step 2
Complete the
Step 3
Complete the
Step 4
Cisco ONS 15454 DWDM Installation and Operations Guide, R4.7
1-66
shows rear cover installation using spacers.
"NTP-G14 Install DWDM Equipment" procedure on page
This procedure installs the optional DWDM assemblies.
#2 Phillips screwdriver
Crimping tool (large enough for #10 to #14 AWG)
#14 AWG wire
NTP-G2 Install the Shelf Assembly, page 1-8
As needed
Onsite
None
"DLP-G27 Install the DCU Shelf Assembly" task on page 1-67
"DLP-G28 Install the Fiber Patch Panel Shelf" task on page 1-68
"DLP-G29 Install the Fiber Storage Shelf" task on page 1-68
"DLP-G8 Install the Air Ramp" task on page 1-19
Chapter 1
Install the Shelf and Common Control Cards
1-66.
as needed.
as needed.
as needed.
as needed.
September 2004