42.5.2
Description
Diagram
Requirements
Field procedure
step-by-step
Reference Line
Working Example
Application:
Reference line/arc:
d1
P1
P2
GPS12_131
•
The reference line does not need to be stored.
•
<Write Logfile: Yes> in REFLINE Configuration, Logfile page.
The following table explains the most common settings. Refer to the stated chapter for more
information on screens.
The positions of stakes, indicating the corners of a house that is
to be built, need to be measured relative to the title boundary of
the property that the house is to be built on.
This is done to check that the house is not being built too close
to the title boundary in keeping with council regulations.
The title boundary is used to define a reference line.
P0 Start point
P1 End point
S1
P2 Reference point
S1 Point to be measured
d2
P0
d1
d2
TPS1200
∆
<
Offset:>
∆
<
Line:>
995