CHAPTER 3: INSTALLATION

U l t i m a S V

MACHINE DELIVERY

When the machine arrives, inspect the entire shipment for damage. If
there is damage, photograph for verification and immediately file a
claim with the carrier.
• Provide competent machinery movers when the machine
arrives
• Note the gross weight of the machine shown on machine
order acknowledgement and on the bill of lading
• Study the mass and weight distribution of the machine
• Refer to the illustration showing recommended lifting
points

PREPARE SITE AND UTILITIES FOR MACHINE

Select the machine site carefully. The structure must support the
machine and production activities. The area should be well lit for oper-
ator efficiency and accessible from all sides for service, maintenance
and operation.
W
:
ARNING
Do not install the machine in a combustible environment or near
explosives.

INSTALLING AIR DEVICES

• Supply clean dry air with a minimum of 65 PSI
• Use pipe that is at least the size of the inlet (minimum 1/2").
A smaller pipe can be used only if a surge tank is in place.
• The following chart may be used as a guide for installing air
devices.
I
:
MPORTANT
The exact consumption may vary slightly. Consumption depends
on model, speed, and auxiliary equipment. Call HayssenSandia-
cre for exact specifications.