7. Start the engine and monitor the charge pressure
gauge to ensure charge oil for the hydrostatic
system; the pressure reading should be 6.8 -
8.2 bar (100 - 120 PSI).
IMPORTANT: If charge pressure remains below 3.4
bar (50 PSI) for more than 10 seconds, stop the en-
gine and locate the cause. If the unit is operated with
low or no charge pressure, severe damage will occur
to the hydrostatic system.
Do not stroke the hydrostatic controls or operate
the boom and bucket control at this time.
8. Allow the engine to operate at 1500 RPM for
about 30 minutes. Stop the engine; check the oil
level and fill as required.
9. Start the engine and operate at 1500 RPM and
slowly operate the hydrostatic system to remove
air, monitor the charge pressure. Operate the
boom and bucket for a few cycles to remove the
air from the hydraulic system.
10. Stop the engine; recheck the hydraulic system oil
level and add as required.
11. Remove the charge pressure test gauge.
12. Adjust the neutral system if required; refer to the
operator's manual for procedures.
13. Run the engine at 1500 RPM for an additional 30
minutes to filter the oil. Stop the engine and
change the oil filter.
14. Check for oil leaks and repair as required.
15. Reinstall all shields removed for repair.
16. Lower the skid-steer loader to the ground and op-
erate.
SECTION 29 - HYDROSTATIC TRANSMISSION
29-70
Copyright © New Holland
147
148

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ls150

Table of Contents