18.7.1

1. Documenting startup

Precondition
As a minimum, the machine name/No., the customer No. and the country where the
manufacturer is located must be entered into the machine identity.
Procedure
Note
2. Perform commissioning
On completion of first commissioning, you will be prompted to perform the 2nd
commissioning.
If the 2nd commissioning is not performed, then you will be prompted at regular intervals to
complete the 2nd commissioning.
See also
Entering machine-specific information (Page 328)
18.7.2
2. Defining start-up
Precondition
As a minimum, the country of the end customer must be entered into the machine identity.
SINUMERIK Operate (IM9)
Commissioning Manual, 03/2013, 6FC5397-1DP40-3BA1
1.
The machine-specific information data are entered.
2.
Start-up (commission) the machine.
3.
Press the "1st startup completed" softkey.
The "1.SETUP" entry is displayed in the "Machine logbook" window
together with the time and date.
Service and diagnostics