DLP-H3 Mount the ONS 15310-MA SDH in a Rack

Purpose
Tools/Equipment
Prerequisite Procedures None
Required/As Needed
Onsite/Remote
Security Level
Mounting the ONS 15310-MA SDH in a rack requires a minimum of 2.75 inches of vertical rack space
Note
(plus 1 inch for air flow). To ensure the mounting is secure, use two #12-24 mounting screws for each
side of the shelf assembly.
If you will install DC power, verify that the proper fuse and alarm panel has been installed in the top
Step 1
mounting space. If a fuse and alarm panel has not been installed, you must install one according to
manufacturer instructions. A fuse panel with two fuses per shelf (amperage depends on the fuse and
alarm panel you are using) is required for Power A and B feeds.
Maximum amperage rating of the fuse is determined by the rated ampacity of the selected power cable
Caution
(refer to manufacturer's instructions). The fuse rating should not exceed 15 Amp.
Install the appropriate bracket for the desired rack size (either 19 or 23 inches). Screw two screws
Step 2
through the bracket into the rack and 4 screws to adhere the bracket to the ONS 15310-MA SDH chassis
Figure 16-1
Cisco ONS 15310-MA SDH Procedure Guide, Release 9.1 and Release 9.2
16-2
Pins are not bent or broken
Frame is not bent
This task allows one person to mount the shelf assembly in a rack.
Two sets of #12-24 mounting screws
#2 Phillips screwdriver
Fuse and alarm panel, if not installed (DC power only)
As needed
Onsite
None
shows the mounting bracket orientations for a 19-inch rack.
Chapter 16
DLPs H1 to H99
78-19416-01