Summary of failure of post charge test in an OPM
Disable battery
audit
Use PES117 log to
identify the battery
string that fails.
Open the circuit to
the battery string that
fails.
Measure the
battery string
voltage that fails.
OPM routine maintenance procedures
Is voltage less than
OPM_VOLT_TST_CHG?
N
Return battery
string pair to
service
DMS-100 Family OPM Maintenance Manual XPM14 and up
Failure of post charge test
OPM
This flowchart summarizes the
procedure.
Use the instructions that
follows this flowchart to
perform the procedure.
Y
Proceed to OPM
site test
End of procedure