Nortel DMS-100 Series Maintenance Manual page 243

Hide thumbs Also See for DMS-100 Series:
Table of Contents

Advertisement

Note: Repeat this step until both units of the LCM are on the selected RG.
If the SWRG command
passes
fails
17
Go to Card Replacement Procedures . Complete the card replacement
procedure. Go to step 11 of this procedure.
18
For additional help, contact the next level of support.
19
The procedure is complete. If the system displays other alarms, refer to the
appropriate alarm clearing procedures for the indicated alarms.
OPM alarm clearing procedures
DMS-100 Family OPM Maintenance Manual XPM14 and up
critical
Do
step 19
step 18
7-23
LCM (RG)
(end)

Advertisement

Table of Contents
loading