2-56 Functional overview
LCM to an XLCM load. When this event occurs, the BRT does not test the
LCM. You must busy the LCM, reload the LCM with an XLCM load and RTS
the LCM. This action includes LCM in the test schedule.
An office-level test or manual LCM-level test attempt can occur on an LCM
with a load that is not changed. When this event occurs, the test does not run.
The system outputs a log that indicates the LCM does not contain an XLCM
load.
You can change the MEMSIZE field from 256 kB to 64 kB. When you
changes this field, the BICTST field must be set to NO. The BICTST field can
be set to NO. When this event occurs, a message appears that indicates that
the BICTST field is set to YES. The value YES is valid only for XLCMs. The
system rejects the change. When you set the MEMSIZE field to 256k, you can
set the BICTST field to YES or NO. The system includes any LCM entry in
table LCMINV, with the MEMSIZE field set to YES, in the test schedule.
BICRELAY command
The BICRELAY command allows you to enable, disable, reset, allow or
disallow the PM181 drawer state to change logs. The drawer state changes
logs when a set LCM undergoes the system BRT. Operating company
personnel can perform the following actions:
The following paragraphs describe the BICRELAY command parameters.
ON
The ON parameter allows the test to begin at the scheduled window. A
message appears that indicates the test is turned ON. When the current data
and time occurs in the scheduled window, the office-level test starts. When
tests are in progress when you issue this command, a message appears. This
message indicates you must wait until all tests are complete before you start
the BRT. This option does not affect the operation of the manual TST
command at the LCM MAP display level.
297-8361-550 Standard 04.02 December 2004
query the ON or OFF state of the BRT
determine when the system allows or suppresses the PM181 drawer-state
change logs
query the number of BRTs in progress
query the next LCM that the system BRT intends to test
Note: The system suppresses the PM181 logs associated with the LCM
undergoing the BRT. The system allows any other PM181 log associated
with any other LCM or XPM.