General
Robots delivered with the Foundry Prime protection are specially designed to work in water
jet cleaning cells with 100% humidity and alkaline detergent. To ensure that the protection
offers the best reliability, some measures are needed during installation of the robot according
to the procedures below.
NOTE!
For best reliability, it is also of highest importance that the special maintenance instructions
for the Foundry Prime robot are followed and documented.
Commissioning
Environmental conditions
Humidity
Washing detergent with pH
Washing detergent must contain rust inhibitor and be
approved by ABB
Cleaning bath temperature
Air specification for pressurizing of robot
The air must be dry and clean, such as instrument air. Following table details the air
specification.
Dew point
Solid particle size
Oil content
Pressure to robot
104
Never switch off the overpressure in motors and serial measurement compartment
during cooling down of robot after it has been switched off.
When turning off an cleaning cell we recommend that the humid air inside a cell is
ventilated out, to avoid that the humid air is sucked into e.g. gearboxes due to the
raised vacuum when cooled down.
100%
<9.0
<60°C, used in a typical waterjet
cleaning application at suitable
speed.
<+2°C at 6 bar
<5 microns
<1 ppm (1 mg/m3)
0.2-0.3 bar
Continues on next page
3HAC020993-001 Revision: G

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Irb 6650s - 125/3.5Irb 6650s - 90/3.9

Table of Contents