1MRK 511 408-UUS A
23.4.2.2
Phasor measurement unit RES670 2.2 ANSI
Technical manual

Mounting procedure for 19" panel rack mounting

2
1a
IEC08000160 V3 EN-US
Figure 335:
19" panel rack mounting details
The required torque for the screws is 3.5 Nm.
Section 23
IED hardware
3
1a
IEC08000160-3-en.vsdx
M11948-2 v6