Communication Protocols - ABB RES670 Technical Manual

Relion 670 series, phasor measurement unit
Hide thumbs Also See for RES670:
Table of Contents

Advertisement

1MRK 511 408-UUS A
Section 19
19.1
19.2
Phasor measurement unit RES670 2.2 ANSI
Technical manual
Station communication

Communication protocols

Each IED is provided with several communication interfaces enabling it to connect to
one or many substation level systems or equipment, either on the Substation
Automation (SA) bus or Substation Monitoring (SM) bus.
Available communication protocols are:
IEC 61850-8-1 communication protocol
IEC/UCA 61850-9-2LE communication protocol
LON communication protocol
SPA communication protocol
IEC 60870-5-103 communication protocol
DNP 3.0 communication protocol
C37.118 communication protocol
Several protocols can be combined in the same IED.
Communication protocol diagnostics
Status of the protocols can be viewed in the LHMI under Main menu/
Diagnostics/IED status/Protocol diagnostics. The diagnostic values are:
Diagnostic value
Off
Error
Warning
Ready
Station communication
GUID-6BC4671F-6D06-4BBD-B1FF-2F03FF16A856 v1
Description
Protocol is turned off
An error has occured, refer to event list for more
information
Configuration inconsistency. Unable to locate data
point.
Protocol is ready
Section 19