Mounting Procedure For Side-By-Side Flush Mounting - ABB RES670 Technical Manual

Relion 670 series, phasor measurement unit
Hide thumbs Also See for RES670:
Table of Contents

Advertisement

1MRK 511 408-UUS A
23.4.5.2
Phasor measurement unit RES670 2.2 ANSI
Technical manual
Please contact factory for special add on plates for mounting FT
switches on the side (for 1/2 19" case) or bottom of the relay.

Mounting procedure for side-by-side flush mounting

2
1
IEC06000181-2-en.vsd
IEC06000181 V2 EN-US
Figure 340:
Side-by-side flush mounting details (RHGS6 side-by-side with 1/2 x 19"
IED).
The required torque for the screws is 3.5 Nm.
PosNo
Description
1
Mounting plate
2, 3
Screw, washer
4
Mounting angle
3
4
Quantity
2
16
2
Section 23
IED hardware
M12730-6 v4
Type
-
M4x6
-
869