Rack-Mount Installation

1.
With one person on each side of the analyzer (two people total), lift the rear of the
analyzer onto the user provided L-brackets.
2. Push the analyzer fully into the rack until the flanges on the front panel of the
analyzer are flush with the outer edge of the rack. Make sure that the mounting
holes on the rack match with the mounting holes on the analyzer's front panel.
3. Insert the user provided mounting hardware through the mounting holes on the
rack and analyzer front panel.
4. Secure the hardware.

Rack Mounting Ventilation and Power Requirements

A continuous flow of air is pumped through the inlet port and out through the
PUMP
port on the back panel of the analyzer. When mounting the analyzer:
Do not block the front or back panels.
Leave at least four inches of free space at the front and back of the analyzer for
proper ventilation and cooling.
Leave sufficient space behind the rack to unplug the analyzer power cord.
When mounting the analyzer in an equipment rack, no side clearance is required.

Emergency Shutdown Procedure

If the analyzer malfunctions and requires emergency shutdown:
1.
Turn off the analyzer using the front panel on/off switch. (Figure 2)
2. Unplug the power cord from the analyzer. (Figure 4)
3. Notify trained service personnel that the analyzer needs repair or servicing.
The analyzer is equipped with a three-prong power plug. The third
prong of the facility electrical outlets must be grounded. Failure to
ground the third prong may result in electrical damage to the
analyzer and electrical shock to the operator.