ABB RES670 Technical Manual page 520

Relion 670 series, phasor measurement unit
Hide thumbs Also See for RES670:
Table of Contents

Advertisement

Section 16
Monitoring
Y
Value Reported
(1st)
IEC99000529 V2 EN-US
Figure 199:
Magnitude dead-band supervision reporting
514
Value Reported
Y3
Y
Y2
Y
Y
Y
Y1
After the new value is reported, the ±ΔY limits for dead-band are automatically set
around it. The new value is reported only if the measured quantity changes more than
defined by the ±ΔY set limits.
Integral dead-band reporting
The measured value is reported if the time integral of all changes exceeds the pre-set
limit (XDbRepInt), figure 200, where an example of reporting with integral dead-band
supervision is shown. The picture is simplified: the process is not continuous but the
values are evaluated with a time interval of one execution cycle from each other.
The last value reported, Y1 in figure
measurement. A difference is calculated between the last reported and the newly
measured value and is multiplied by the time increment (discrete integral). The
absolute values of these integral values are added until the pre-set value is exceeded.
This occurs with the value Y2 that is reported and set as a new base for the following
measurements (as well as for the values Y3, Y4 and Y5).
The integral dead-band supervision is particularly suitable for monitoring signals with
small variations that can last for relatively long periods.
Value Reported
Y
Y
200
serves as a basic value for further
1MRK 511 408-UUS A
Value Reported
IEC99000529-2-en.vsdx
Phasor measurement unit RES670 2.2 ANSI
Technical manual
t
SEMOD54417-167 v4