3
Connecting the cables
1
2
Configuring the lead-through functionality
The lead-through functionality is predefined for robots that are delivered with the
option 3313-1 Lead-through Device ordered.
If the lead-through option is newly ordered for an existing robot and the robot
system is operating in RobotWare 7.6 or later, the Collaborative Speed Control
add-in must be installed to the system to activate the lead-through functionality.
For details about how to install the add-in and configure the lead-through
functionality, see
Product manual - CRB 1100
3HAC078007-001 Revision: J
Action
Turn the adjusting knob to lock the lead-through
device.
Note
Do not use excessive force!
The arrow in the figure indicates the direction of
locking the lead-through device.
Action
Connect the cabling between the lead-through
device and robot.
R2.C2 connector on process hub of robot
(A)
Lead through device connector (B)
Connect the cable between robot and controller.
R1.C2 connector on robot base (A)
Ethernet switch port on controller (B)
X19 connector on controller (C)
Note
Ethernet switch port is available for use only when
the 5 Port Ethernet switch option is selected.
Otherwise, connect the cable to the MGMT port.
Note
Pins 3 and 4 of X19 connector are used for the
lead-through device connection while pins 1 and
2 are occupied by the CP/CS cable for lamp unit.
Lead-through on page
© Copyright 2021-2023 ABB. All rights reserved.
3 Installation and commissioning
3.3.7 Installation of lead-through device
Note
xx2200000765
Note
xx2200000766
A
xx2100000292
97.
Continued
B
C