Lucent DDM-2000 OC-3 User And Service Manual page 479

Tarp release 13 and later volume ii
Table of Contents

Advertisement

NTP-050
: System Turnup
Page 9 of 14
DO ITEMS BELOW IN ORDER LISTED. . . . . FOR DETAILS, GO TO
21. Repeat this procedure from Step 16 for all OC-3 optical spans
being established in the DDM-2000 OC-12/OC-3 network. Ensure
that the last optical span connected to the OC-12 host shelf is
connected to an OLIU in the opposite slot as the one in the first
host OC-12 (for example in Figure 3, slot 1 at one host node and
slot 2(P) at the other host node).
22.
NOTE:
Establishing service requires that the proper slots in each
terminating node be properly equipped with the correct
circuit pack(s) for the type of service being established. It
also requires numerous cross connections in each of the
nodes representing the path of the required service.
Additionally, transmission tests should be performed to verify
the continuity and quality of the established circuit.
The dual-homed DDM-2000 OC-3 access network is now ready
for initial service to be established. For DS3, EC-1, STS-3c, and
video terminations on a DDM-2000 OC-12 shelf, use the
procedures 363-206-295, DDM-2000 OC-12 Multiplexer, TARP
Release 7, User/Service Manual (TOP)—Volume II to establish
those services. For DS1, DS3, EC-1, T1, HDSL, STS3c, and/or
LAN terminations on a DDM-2000 OC-3 shelf, use the procedures
in this 363-206-285, DDM-2000 OC-3 Multiplexer, TARP Release
13 and Later, User/Service Manual (TOP)—Volume II to establish
those services.
DDM-2000 OC-3 M
Issue 2, February 2000
ULTIPLEXER
363-206-285