363-206-285
Issue 2, February 2000
DO ITEMS BELOW IN ORDER LISTED . . . . .FOR DETAILS, GO TO
10.
NOTE:
Ring releases support only manual VT1.5 and STS-1
cross-connections. Manual STS-1 and/or DS1
cross-connections have to be made at each shelf to
configure the transmission path for each DS3/DS1 circuit
being established. Either terminating (drop)
cross-connections or "drop and continue" cross-connections
are made at terminating nodes and pass-through
cross-connections are made at intermediate nodes.
NOTE:
In ring configurations, you should use the following rules in
establishing cross-connections in each ring:
1.
All drop connections (including DRI, if present) from
the same STS-1 timeslot must be provisioned the
same, either all VT1.5 or STS-1.
2.
If all 28 VT1.5s (DS1s) in an STS-1 are being passed
through at a node in a VT1.5 path-switched ring, then
the cross-connection may be provisioned as either a
pass-through STS-1 or VT1.5. However, if you
anticipate dropping VT1.5s from the pass-through
node in the future, you should provision the
pass-throughs as VT1.5 cross-connections. OC-3 ring
Releases 7.0 and earlier do not support the command
(cnvt-crs) for converting an STS-1 to a VT1.5
cross-connect. Also, provisioning now as a VT1.5
cross-connect will avoid a hit on traffic if the STS-1
cross-connect has to be converted to 28 VT1.5
cross-connects to drop DS1s at a later time.
3.
On STS-1 path-switched rings, all nodes in the ring
must be provisioned as STS-1 cross-connections.
DDM-2000 OC-3 M
System Turnup:
ULTIPLEXER
NTP-033
Page 4 of 6