DO ITEMS BELOW IN ORDER LISTED . . . . .FOR DETAILS, GO TO
At the DDM-2000 shelf, use the ent-ulsdcc-l3: command to
designate the NSAPAREA field and level 2 IS-IS routing, as
required.
At the WaveStar TDM 2.5G shelf, use the appropriate
menu/toolbar to designate the L3 Area address and Level 2 IS
parameters, as required.
16.
NOTE:
The rtrv-pm-line: command in the following procedure
displays performance monitoring data associated with the
OC-3/OC-12 lines terminated on the system.
Perform end-to-end OC-3/OC-12 line test.
17. Repeat this procedure from Step 12 for all OC-3/OC-12 optical
spans until the OC-3/OC-12 linear extension is complete back to
the host WaveStar TDM 2.5G shelf.
18.
NOTE:
Establishing service requires that the proper slots in each
terminating node be properly equipped with the correct
circuit pack(s) for the type of service being established. It
also requires numerous cross connections in each of the
nodes representing the path of the required service.
Additionally, transmission tests should be performed to verify
the continuity and quality of the established circuit.
The OC-3/OC-12 linear extension is now ready for initial service
to be established. For service terminations on a WaveStar TDM
2.5G shelf, use the procedures in 365-371-102, WaveStar TDM
2.5G, User/Service Manual , to establish those services. For DS1,
DS3, EC-1, STS3c, T1, HDSL, and/or LAN terminations on a
DDM-2000 OC-3/OC-12 shelf, use the procedures in this
User/Service manual to establish those services.
DDM-2000 OC-3 M
System Turnup:
ULTIPLEXER
NTP-059
Page 8 of 12
DLP-515