Lucent DDM-2000 OC-3 User And Service Manual page 550

Tarp release 13 and later volume ii
Table of Contents

Advertisement

363-206-285
Issue 3, June 2001
DO ITEMS BELOW IN ORDER LISTED . . . . .FOR DETAILS, GO TO
At the DDM-2000 shelf, use the ent-ulsdcc-l3: command to
designate the NSAPAREA field and level 2 IS-IS routing, as
required.
At the FT-2000 shelf, use the
CONFIGURATION-Set-ULSDCC-L3 command to designate the
L3 Area address and Level 2 IS parameters, as required.
18.
NOTE:
The rtrv-pm-line: command in the following procedure
displays performance monitoring data associated with the
OC-3/OC-12 lines terminated on the system.
Perform end-to-end OC-3/OC-12 line test.
19. Repeat this procedure from Step 14 for all OC-3/OC-12 optical
spans until the OC-3/OC-12 linear extension is complete back to
the host FT-2000 shelf.
20.
NOTE:
Establishing service requires that the proper slots in each
terminating node be properly equipped with the correct
circuit pack(s) for the type of service being established. It
also requires numerous cross connections in each of the
nodes representing the path of the required service.
Additionally, transmission tests should be performed to verify
the continuity and quality of the established circuit.
The OC-3/OC-12 linear extension is now ready for initial service
to be established. For service terminations on a FT-2000 shelf,
use the procedures in 365-575-103, FT-2000 OC-48 Lightwave
System, Release 8.1 Through 9.1, User/Service Manual , to
establish those services. For DS1, DS3, EC-1, STS3c, T1, HDSL,
and/or LAN terminations on a DDM-2000 OC-3/OC-12 shelf, use
the procedures in this User/Service manual to establish those
services.
DDM-2000 OC-3 M
System Turnup:
ULTIPLEXER
NTP-057
Page 8 of 12
DLP-515

Advertisement

Table of Contents
loading

Table of Contents