3 Installation and commissioning

3.2 Installation activities

3.2 Installation activities
Main steps for installing the controller
Use the following main steps to unload, transport, install, and connect the controller.
1
2
3
4
5
6
7
8
9
52
Action
Unpack the controller.
Install the controller.
Connect the manipulator to the controller.
Connect power supply to the controller.
Connect input signals for presence sens-
ing devices, etc.
Connect the FlexPendant to the controller.
Connect, for example, EtherNet, antenna,
PC, and other connections.
Install options and add-ons (optional).
Initial test before commissioning.
© Copyright 2020-2021 ABB. All rights reserved.
Described in
Unpacking the controller on page
On-site installation on page
Connecting the manipulator to the control-
ler on page
71.
Connecting power supply to and grounding
the controller on page
75.
Connecting and detaching a FlexPendant
on page
78.
How to connect industrial networks, for
example EtherNet, is described in the re-
spective application manual.
How to connect to a network and a PC is
described in section
Set up the network
connection on page
86. See also Operating
manual - RobotStudio.
See also
Descriptions for connectors on
page
89.
Installing options on page
Installing add-on devices on page
Initial test before commissioning on
page
160.
Product manual - OmniCore C90XT