The feet will be used for positioning and fastening.
Mounting requirements:
Product manual - OmniCore C90XT
3HAC073706-001 Revision: E
41
Anchor bolts: M8 X 4
Tightening torque: 11.3 Nm-12.6 Nm
Maximum flatness deviation of the installation plane: 8 mm
Note
Fix the controller to a concrete foundation or steel platform with anchor bolts
during stacking.
Note
According to IEC60204-1, the power-operated switch should be installed between
600 mm to 1,900 mm above the servicing level. The switch will be easily
accessible.
© Copyright 2020-2021 ABB. All rights reserved.
3 Installation and commissioning
3.4.1 Required installation space
418