30.3.5 Items to be checked before starting drawing

The following describes that should be understood before starting drawing and the functions that should be set
beforehand when using the multi-channel function.
Device settings
It is necessary to set the device to be used together with the CH No.
GT Designer3 Version1 Screen Design Manual
Click the device setting button.
Accessible range for monitoring
The accessible range for monitoring is not changed even when the multi-channel function is used.
GOT1000 Series Connection Manual for GT Works3
Clock function
Set the controller for which adjust/broadcast should be executed by the CH No.
GT Designer3 Version1 Screen Design Manual
Broadcast is
executed for
CH No.1
Click the controller to be set.
10:10
10:10
CH No.1
FXCPU
CH No.2
QCPU
30. MULTI-CHANNEL FUNCTION
30.3 GOT Side Settings
Set the device.