Switch monitoring on;
Limiting lifting
Lift the load to the necessary height.
Select the symbol (1).
Press the button (6) or (7) once.
The current numerical value (5) is set at
the symbol (2) as the upper limit value,
symbol (1) confirms the entry.
Limiting lowering
Lower the load to the necessary height.
Select the symbol (4).
Press the button (6) or (7) once.
The current numerical value (5) is set at
the symbol (4) as the lower limit value,
symbol (3) confirms the entry.